Summary: The Kelantan state government is targeting 200 EV charging bays across the state by 2030, up from 39 bays on its records today. Kota Bharu gets 65 of the planned bays, and the other 135 are spread across Tumpat, Kuala Krai, Tanah Merah, Jeli, Machang, Pasir Puteh, Bachok and Gua Musang. State executive councillor Hilmi Abdullah announced the target in a written reply at the Kelantan State Assembly on 4 November 2026. The state has not said whether the bays will be AC or DC fast chargers, or who will build and run them.

If you’ve ever driven an EV home to Kelantan for Hari Raya, you know the feeling. Battery at 40%, Gua Musang still a while away, and a quiet prayer that the charger you’re heading for isn’t full.

Kelantan EV charging is about to get a push. The state wants 200 public charging bays by 2030, more than five times the 39 it has on record now, and it has already told local councils where it wants most of them to go. For anyone doing the balik kampung drive, that means more places to top up outside Kota Bharu over the next few years. So can you drive an EV home for Raya or not? You can lah, and it’s going to get easier.

Below you’ll find the district-by-district plan, the planning rule that now makes new car parks include EV bays, how the numbers stack up nationally, and what to expect on your next Raya trip. Our own view sits near the end, because we think the 200 figure is the least interesting part of this announcement.

What did Kelantan announce?

According to Harakah Daily, the Kelantan state government is targeting 200 EV charging bays across the state by 2030, up from 39 bays on record today. The target came from Hilmi Abdullah, who chairs the state committee for Local Government, Housing, Health and Environment.

He gave it in a written reply to a question from Wan Rohimi Wan Daud (PAS, Melor) at the sitting of the 15th Kelantan State Assembly at Kompleks Kota Darulnaim, Kota Bharu, on 4 November 2026. The stated reason is to get ready for more EV users in Kelantan, including tourists driving in from other states.

The reply also covered a few smaller plans:

  • Kota Darulnaim: the state will try to provide 2 EV charging bays at the state government complex.
  • Civil servant car loans: Hilmi suggested the state review the vehicle types allowed under its car loan scheme for civil servants, so that EVs can be included.
  • Government vehicles: he agreed the state should study switching official vehicles to EVs, saying it could cut maintenance, diesel and petrol costs. This is a study, not a decision.

So Where will Kelantan’s 200 EV charging bays go?

Kota Bharu (the MPKB-BRI council area) gets the biggest share with 65 bays, and the remaining 135 bays go to the other districts. The split below is based on proposals the state has received. The shares are our own calculation.

Area Planned bays Share of 200
Kota Bharu (MPKB-BRI) 65 32.5%
Tumpat 30 15%
Tanah Merah and Jeli 25 12.5%
Pasir Puteh and Bachok 25 12.5%
Kuala Krai 20 10%
Gua Musang 20 10%
Machang 15 7.5%
Total 200 100%

The interesting bit is how much this spreads things out. Today, 37 of the 39 recorded bays (about 95%) sit in the Kota Bharu council area, and only 2 are elsewhere, one of them at a McDonald’s outlet. Under the plan, Kota Bharu’s share drops to roughly a third.

The pace is steady rather than dramatic. Going from 39 to 200 means adding 161 bays in about four years. That’s roughly 40 a year, or three to four a month across the whole state.

Two pairs (Tanah Merah with Jeli, and Pasir Puteh with Bachok) were grouped together in the reply, so we don’t yet know how those bays will be split between the towns.

Is the real number of EV chargers in Kelantan higher than 39?

Almost certainly, yes. The state itself said some chargers were never registered with the local councils (PBT), so the real figure is likely higher, and councils have been told to collect data to get an accurate count.

Our own check of public launch reports backs this up. Outside Kota Bharu, charging operators have opened these sites over the past two and a half years:

  • Gua Musang: a DC Handal 47kW DC charger with two connectors at Hentian Gua Musang (opened April 2024), a Gentari 200kW DC charger with four bays at G-Orange Mall (March 2025), and JomCharge DC and AC chargers for up to three cars at the Tengku Muhammad Fa-iz Petra Mosque (September 2025).
  • Jeli: a TNB Electron DC charger, advertised at up to 240kW, at Petron Batu Melintang (October 2025).
  • Pasir Puteh: a TNB Electron DC charger at Petron Selising (October 2024).

That’s around nine charging points in Gua Musang alone, against the “2 elsewhere” in the official tally. So if you’re planning a trip, don’t go by the state’s number. Check PlugShare or the operators’ own apps (ChargEV, JomCharge, Gentari Go, TNB Electron) for what’s live and working on the day.

What does this mean for Kelantan EV charging on the balik kampung drive?

It will get easier to drive an EV home to Kelantan for Hari Raya, but the bigger gains from this plan will come over the next few years, not by next Raya. Hari Raya Aidilfitri 2027 is expected around 10 March 2027 (subject to moon sighting), and most of the 200 bays won’t exist by then.

The inland route is already doable. A few years ago, most EV drivers avoided the Gua Musang road because there were no public DC chargers on it. That changed with the three Gua Musang sites listed above.

What the state plan adds is more spots to charge once you’re inside Kelantan. Gua Musang, Kuala Krai, Machang, Tanah Merah and Jeli together get 80 of the planned bays. For a Raya drive, that matters in two ways:

  • Shorter queues at peak. Raya traffic is when a single busy charger hurts most. More bays spread across district towns means fewer cars piling onto one site.
  • Charging near the kampung. Even slower AC bays at a council car park or market are handy when you’re staying a few days and the family home has no suitable socket.

One caution: if you plan to plug a portable charger into a socket at your family’s house, get the wiring checked first by an ST-registered electrician. Older kampung wiring wasn’t built for hours of continuous load. Want to know what a full top-up costs at home versus a DC charger? Run the numbers in our EV charging cost calculator.

What is the EVCB guideline, and what does it mean for new car parks?

The EVCB guideline is the national planning rule that requires new developments to set aside at least 2% of their total parking spaces as EV charging bays. The guideline also calls for at least one EV charging bay in visitor parking where that applies, and encourages at least one bay for electric motorcycles in every development.

Here’s how it reached Kelantan:

  • September 2023: the National Physical Planning Council (MPFN) approved the Electric Vehicle Charging Bay (EVCB) Planning Guideline.
  • October 2023: KPKT launched the guideline and the EVCB application procedure.
  • April 2024: Kelantan’s State Planning Committee approved it.
  • October 2024: the State Executive Council adopted it.
  • January 2025: the decision went out to all Kelantan local councils for implementation.

Councils now use the guideline to assess applications and to set charging bay conditions in planning permission. In plain numbers, a new mall with 300 parking spaces would need at least 6 EV bays, and a 1,000-space development would need at least 20.

How long does it take to get an EV charger approved in Kelantan?

Kelantan’s local councils must approve private EV charger applications within 14 working days. MITI has quoted the same 14-working-day timeline for the guideline nationally.

There’s still a catch. Each application needs technical comments from TNB (on whether the power supply is enough), Bomba (the fire department) and the charging operator. For a DC fast charger, which draws far more power, the TNB supply review is the step most likely to slow things down. We cover how that works in our guide to TNB approval for EV charger installation.

Councils have also been asked to identify suitable sites early, such as public car parks, markets, commercial centres, government complexes, transport terminals and housing areas.

If you run a hotel, mall or shoplot in Kelantan and want to host chargers, remember the basics: chargers sold in Malaysia need Energy Commission (Suruhanjaya Tenaga) approval, with SIRIM testing and certification now required, and only ST-registered contractors may legally install one.

How does Kelantan’s target compare with the national numbers?

Kelantan’s 200 bays would be well under 1% of Malaysia’s current national target of 30,000 public chargers by 2030. MITI gave that 30,000 target in July 2026.

The state reply cited a national target of 10,000 charging bays by 2030 and about 6,000 bays available now. Those figures don’t match the official record, so here’s what we found:

  • The 10,000 target was for 2025, not 2030. The Low Carbon Mobility Blueprint aimed for 10,000 public charging points by 2025. Malaysia reached 5,624 by 31 December 2025, according to MITI.
  • The latest count is 6,416. MITI says Malaysia had 6,416 public EV chargers as of 31 May 2026, made up of 2,143 DC fast chargers and 4,273 AC chargers.
  • The new goal is 30,000. MITI has since set a target of 30,000 public chargers nationwide by 2030.

For a sense of scale, Penang’s Chief Minister announced a target of 600 charging bays by 2030 back in April 2026, three times Kelantan’s figure.

Our take: the planning rule will do more for Kelantan than the 200-bay target

We think the 200-bay target is useful but modest, and the EVCB planning rule will end up adding more chargers to Kelantan than any state target. This is EV Charge Malaysia’s opinion, not an official position.

Our reasoning comes down to three numbers. First, 200 bays for a whole state is small: about 40 new bays a year, with most districts getting 15 to 30 each by 2030. Second, private operators have already done much of the heavy lifting on the route that matters most for travellers, with roughly nine charging points in Gua Musang that don’t appear in the official count. Third, the 2% rule grows with every new car park and costs the state nothing, so it keeps adding bays long after 2030.

The plan’s real value, in our reading, is the spread. Moving from 95% of recorded bays in Kota Bharu to about a third is what will help people in Machang, Kuala Krai and Pasir Puteh. Tumpat getting 30 bays, more than Kuala Krai, also hints at tourism and border traffic around the coast and Pengkalan Kubor. That’s our interpretation of the split, not something the state said.

The strongest counter-argument is a fair one. Charging operators chase traffic, and they may never put a charger in a smaller town without a push. The 2% rule only kicks in for new developments, and smaller Kelantan towns don’t see many of those. Seen that way, a state target that names districts and lines up council sites is exactly what’s needed to fill the gaps the market skips.

Where we land: the target helps most in the district towns, provided some of those bays are DC and not only slow AC. The most useful next step the state could take is to publish its updated charger count, the AC and DC mix, and who the operators will be. Until then, we’d treat the 200 as a direction, not a delivery schedule.

Frequently asked questions

How many EV charging bays are there in Kelantan?

The Kelantan state government has 39 EV charging bays on record, with 37 in the Kota Bharu council area and 2 elsewhere. The state admits some chargers were never registered with the local councils, so the real number is higher. Operator launches show several DC fast chargers in Gua Musang, Jeli and Pasir Puteh that sit outside that count.

Can you drive an EV from KL to Kota Bharu?

Yes, you can. The route through Gua Musang now has DC fast chargers at Hentian Gua Musang, G-Orange Mall and the Tengku Muhammad Fa-iz Petra Mosque, so most EVs can make a single top-up stop. Check live charger status in the operator apps before you leave, especially during Hari Raya.

Where can I charge my EV in Gua Musang?

Gua Musang has DC chargers run by DC Handal at Hentian Gua Musang, Gentari at G-Orange Mall, and JomCharge at the Tengku Muhammad Fa-iz Petra Mosque. Kelantan also plans 20 more charging bays in Gua Musang by 2030. Check PlugShare or the operators’ apps for current availability.

How many EV chargers does Malaysia have?

MITI says Malaysia had 6,416 public EV chargers as of 31 May 2026. That total was made up of 2,143 DC fast chargers and 4,273 AC chargers. The government’s target is 30,000 public chargers by 2030.

Do new buildings in Malaysia need EV charging bays?

Yes. Under PLANMalaysia’s EVCB planning guideline, new developments must set aside at least 2% of their total parking spaces as EV charging bays. Local councils set these as conditions in planning permission.

How long does EV charger approval take in Kelantan?

Kelantan’s local councils must approve private EV charger applications within 14 working days. Applications still need technical comments from TNB, Bomba and the charging operator, and the TNB power supply review can take longer for DC chargers.